London 2012 Olympic Games Stadium Trivia, Facts & Figures
London 2012 Olympic 80,000 seat stadium has opened ahead of schedule. (29th March 2011)
It took 1,000 working days and cost £486 million and £10 million under the budget of £496m.
The track has not been layed due to all the construction work that is required.
World class athlete & 4 times sliver medalist Frankie Fredericks & now IOC member layed the final piece of turf.
The stadium work started in May 2008 and has taken less than 3 years.
Olympic Stadium Trivia.
5,200 + people involved in the stadium project. (Workers etc)
90,000 = the size of the square meter infield area.
80,000 = number of seats for the Olympic Games.
40,000 = number of acres that the stadium is situated in.
1,000 - number of working days to build the stadium in Stratford east London.
860 = meters of the stadium perimeter.
532 = number of individual flood lights
486 = cost in millions of the stadium was £486 million
240 = £240 million was the original un relaistic bid to build the stadium
230+ number of British business involved in the project
60 m = Height of the stands
34 = the number of months to build the stadium
14 = number of Towers in the Olympic stadium
5 = number of new bridges built to have access to the 2012 stadium
3 = number of sides of the stadium are covered by water.
3 =number of days to lay all the turf